What the proposal and project agreement contain
Every engagement is written down before work starts, in a proposal that becomes the project agreement once you approve it. It is meant to be read by both a technical lead and a finance or legal reviewer, so it uses plain language and names specific things rather than general intentions.
- Goal and success measures: the business problem, the primary metric, the guardrail metrics and how each is measured.
- In scope and out of scope: what will be built and, just as important, what will not.
- Deliverables: software, documents, evaluation sets, runbooks and training, each listed by name.
- Milestones and acceptance criteria: what is delivered at each milestone and how you will check it.
- Assumptions and dependencies: access, data, people and decisions we need from your side, with the effect of delays.
- Team and governance: named roles on both sides, the weekly rhythm and the gate reviews.
- Security and data handling: access plan, data handling terms and, where needed, a data processing agreement.
- Commercial terms and ownership: the fixed quote, payment schedule and intellectual property clauses.
Milestones and how acceptance works
Work is divided into milestones that each end with something you can see and check. Acceptance is tied to criteria agreed in the proposal, not to a general feeling that the work is done.
| Milestone type | Typical acceptance check |
| Discovery readout | Report, ROI model and roadmap delivered and walked through with your sponsor |
| First working version | Runs on real or representative data, with first evaluation scores shown |
| Integration and controls | Connected to the agreed systems, with approval steps, logging and access controls in place |
| Pilot evaluation | Evaluation report against the agreed metrics, and the go, adjust or stop decision recorded |
| Handover | Code, documentation and runbooks in your repositories, and a walkthrough completed with your team |
Note that a pilot milestone is accepted when the evaluation is delivered honestly, not only when the targets are met. A pilot that shows an idea does not work has still done its job.
How change requests work
Weekly releases mean you will learn things during the project, and some of them will change what you want. That is expected. What matters is that changes are visible and decided by the right person.
- Raise it: either side can propose a change, in the weekly update or at any time.
- Assess it: we write a short change request: what changes, why, the effect on timeline, quote and risk, and any alternatives, such as swapping out something of similar size.
- Decide it: your sponsor approves or rejects it in writing. Small technical choices inside the agreed scope do not need a change request; anything that changes scope, cost, risk or dates does.
- Record it: the decision goes into the decision log, and the plan is updated.
Nothing outside the agreed scope is built, and nothing is billed, without an approved change request.
What an Ongoing Partnership covers
After a pilot or a launch, some clients want us to keep running and improving the system. An Ongoing Partnership is a monthly engagement with clear deliverables, agreed in advance. A typical arrangement combines some of the following, depending on what you need:
- Monitoring of quality, cost and incidents, with a regular report.
- Evaluation runs on every change and on sampled production traffic.
- Model and dependency upgrades, tested before release.
- A backlog of improvements or new use cases, prioritized with your product owner.
- Support for your team, with agreed contact routes and escalation.
The deliverables are reviewed together on a regular basis, so the partnership keeps matching what the business needs. See AgentOps and managed agents and managed DevOps support for what ongoing work looks like in each practice.
Code ownership, stopping and handover
Unless the project agreement says otherwise, all intellectual property created during an engagement, including code, prompts, evaluation sets and documentation, transfers to you on full payment. We work in your repositories from the start, so ownership is practical and not just contractual. Open-source libraries keep their own licenses, which are listed in the handover documentation. We retain only general knowledge and techniques.
You can stop after any phase and keep everything you have paid for. If you decide to stop, we hand over the current state of the code and documents, remove our access and confirm in writing what was removed. If you continue with another partner or your own team, the decision log, runbooks and design records are written so they can pick up where we left off. Our full method is on How we work, and the first month is described on Your first 30 days.